Page 102 - CITS - Electrician - Trade Practical
P. 102

ELECTRICIAN - CITS



           4  Check the connections and ensure that auto transformer knob in zero position..
           5  Switch ON the supply and slowly increase the voltage in  auto transformer until LV side ammeter reads rated
              full load current of transformer.
           6  Record readings of voltmeter, ammeter and watt meter.
           7  Switch OFF the supply and disconnect the transformer and meters

                                                     Tabular column:

                                Voltage            Current             Watts               Total loss
                                (V)                (I)                 (W)


            OC Test to measure
            iron losses (WI)                                                               W  = W + W C
                                                                                                  I
                                                                                             T
            SC Test to measure
            copper losses  (WC)














































           Safety precautions:
           1  Do not make loose & wrong connections.
           2  Do not apply more voltage while conducting SC test.

           3  Check the voltage range of watt meter before switching ON the circuit .
           4  While conducting  SC test  do not short the LV terminals for long time, it may overheat and damage the
              transformer.






                                                           85

                                    CITS : Power - Electrician & Wireman - Exercise 42