P. 347
v
ELECTRICIAN - CITS
2 Install the power cable, with conduit or racking or by UG Cabling
3 Install the charging stations as per the OEMs instructions.
4 Install Circuit breaker
5 Install RCCB, surge protection devices as recommended by manufacturer
6 Do permanent copper wire earthing
7 Verify electrical wiring.
8 Test Supply voltage
9 Test voltage between neutral and earth and verify it to be less than 2volts
10 Test insulation resistance between conductors and earth.
11 Connect charging stations to communication management system platform and verify the firmware update
12 Verify indicator for Switch ON/OFF, Stand-by/charging, Availability status (operational/non-operational), safety
lights, charging completion indication
13 Ensure availability of safety and traffic guidelines signage for customers
14 Clean the site and dispose the garbage.
15 Prepare a detailed installation report.