           TASK 2: Test various sections of EV installation

           1  Calibrate pilot signal CP(control pilot – Type 2 charging), in case of failure of communication between EV and
              EVSE , for correct performance.

           2  Test for continuity in the pilot wires, which are located on the connector.
           3  Examine EV charging cable, and charging station for issues.
           4  Check the charger screen or LED for fault indicators.
           5  Verify the station is online if networked and is updated with the latest firmware.
           6  Update the firmware over the air without opening EVSE, If firmware or network related issue arise.

           7  Check the on-board charger intake current rating and that of EV charger for slow charging issues.
           8  Check communication to CMS (Charging Management System), mobile app if any.
           9  Check wires are fitted properly.
           10 Check if all connectors are mounted properly.
           11 In case of overheating switch OFF the charger.

           12 Check pre-conFigured load balancing setting of EV charger, in case of slow charging problem with fast charger
           13 EV Chargers which is coming with mobile app / digital interface will show the cause of failure / error code in
              user interface area. Refer the use manual for error codes.