           EXERCISE 25 : Testing of protective multiple earthing

                                     (PME) connection


            Objectives
           At the end of this exercise you shall be able to
           •  identify and test the Earthing installations
           •  measure the earth potential between phase & neutral
           •  connect and test the protective multiple earthing (PME) system.

           Requirements

           Tools/Equipments                                    Materials
           •  Combination Plier (165mm, insulated)   - 1 No.      •  PVC copper wire 1.5 sq.mm    - as reqd
           •   Screw Driver 150mm                - 1 No.       •  Test lamp 100 W, 230 V        - 1 No.
           •   Neon Tester 75mm, 500 V           - 1 No.
           •   Electrician knife Insulated       - 1 No.
           •   Multi meter Digital, 3  digit     - 1 No.
                                1/2

            Procedure

           Protective Multiple Earthing (PME) system : It is a method of earthing system in which an earth conductor is
           connected to the earthing point as well as neutral wire of main incoming supply. In this type of connection a fault
           current flows to ground and ensures protection from electric shock and damage of equipments in the event of
           failure/break of main supply neutral wire. This method is often used in power supply & distribution networks.
           TASK 1 : Check the earth continuity
           1  Draw the connection diagram of protective multiple earthing (PME) system.
           2  Identify and test the earthing installation/s for working condition with test lamp.

           3  Identify the main input supply and load switch of electrical installation.

           TASK 2 : Connect and test the protective multiple earthing (PME) circuit
           1  Switch OFF the main incoming supply of electrical installation.

           2  Connect the earth conductor parallel to the earthing point and main neutral wire.
           3  Check the connection and switch ON the supply, measure the earth potential with phase & neutral.
           4  Test the PME circuit by breaking / disconnection of neutral wire and measure the voltage and current  in the
              load circuit.
           Safety precautions:
           1  Do not make connection with live supply.
           2  Do not make wrong & loose connections.

           3  Ensure proper continuity of earth source.