           EXERCISE  31 : To build up the voltage in DC shunt Generator


            Objectives

           At the end of this exercise you shall be able to:
           •  check and identify the terminals of DC shunt Generator
           •  start & run DC shunt Generator with prime mover
           •  build up the voltage in DC shunt Generator
           •  record the field current & induced voltage in the Generator and plot OCC graph.

           Requirements

           Tools/Equipments/Instruments
           •  Combination Plier 165mm,                         •  Ammeter MC, 5 A                -1 No.
                                                                                    1/2
              insulated                         -1 No.         •  Multi meter Digital, 3  digit     -1 No.
           •  Screw Driver 150mm, insulated     -1 No.         •  Rheostat 700 Ω, 5A             -1 No.
           •  Neon Tester 75mm, 500 V-1 No.                    •  Tacho meter 3000 RPM           -1 No.
           •  Electrician knife insulated       -1 No.         Materials/Components
           •  MG set (AC to DC) with DOL starter,              •  Test lamp 60 W, 230 V          -1 No.
              DC shunt Generator 5 KW, 250 V    -1 No.         •  Connecting wire 2.5 sq.mm      - as reqd.
           •  Voltmeter MC, 250 V                        -1 No.    •  Cotton waste / cloth       - as reqd.


            Procedure
           TASK 1 : Check the MG set details & terminals

           1  Clean the MG set with cotton waste and read its specifications.
           2  Draw the circuit diagram of voltage build up of DC shunt generator.
           3  Check and identify the terminals of MG set (AC induction motor and DC shunt Generator)


           TASK 2 : Connecting & Starting of MG set
           1  Make the connection of prime mover AC induction motor with DOL starter.

           2  Make the connection of DC shunt Generator with field rheostat and meters.
           3  Check all connections and keep the rheostat in cut in position.
           4  Switch ON the mains and start the prime mover AC induction motor coupled with DC shunt Generator and
              measure the speed with Tacho meter.


           TASK 3: Build-up the voltage in DC shunt Generator
           1  On starting of MG set observe & record the induced residual voltage in voltmeter.
           2  Slowly increase the field current in DC shunt Generator by adjusting field rheostat.
           3  Further increase the field current until rated voltage (230 V) is build up in DC shunt Generator.
           4  Record the field current and full rated voltage build up in DC shunt Generator.
           5  Reduce the voltage to zero by adjusting field rheostat and stop the prime mover motor.

           6  . Plot the graph to indicate the field current (IF) & induced voltage (E ).
                                                                          G
           Safety precautions:
           1  Ensure proper foundation and perfect coupling of MG set, else it may cause severe injury.
           2  Ensure proper direction of rotation of DC generator to avoid demagnetizing of field poles and fails to build up
              voltage.