TASK 4: Decide and Fill the planned start date and end date
Do backward and forward planning for deciding the planned date for the task. Then add dates against the
tasks. Where processes required multiple days add a planned completion date Note the name of the person
or department who is responsible for the task Keep the “Actual date of start and end” column blank during TNA
calendar preparation.as shown in fig.
Company Name
Time and ac on calendar
Buyer Orient Interna on Order No. 2241 Expected Delivery 20.4.2024
Style# 212 Order Qty. 2,000 pcs Ex-factory Date: 15.04.2024
D o i t p i r c s e n a T T k n o p M a h c r e t n X Z Y a e L i t d m e 4 d 9 s y a
Process Planned Planned Planned Actual Actual Actual Responsibility Remark
# Start End Dura on(days) Start End Dura on
1 Order 16 Feb Merchant
Receipt(Buyer P.O)
2 Consump on 17 Feb Pa ern Master
Calcula on
3 BOM Genera on 20 Feb Merchant
4 PO Issue for fabric 21 Feb Store
trim etc. Manager(Fabric/trim
)
5 Size set Submission 25 Feb Merchant
6 Size set comments 28 Feb Merchant
7 PO mee ng 1 March Merchant
8 Produc on 11 Produc on Manager
Planning march
9 Fabric in House 2 march Store
Manager(Fabric/trim
)
10 Trim in house 2 March Store
Manager(Fabric/trim
)
11 Fabric checking 3 March Fabric Checker
12 Dyeing 3 March 6 March Dyer
13 Prin ng 6 March 8 March Printer
14 Cu ng 8 March 10 Cu ng incharge
March
15 Embroidery 10 15 Embroidery Incharge
March March
16 Fabrica on/ 16 26 Produc on manager
s ching March March
17 Finishing 26 31 Finishing manager
March March
18 Packing & 31 3April
Packaging March
TASK 5: Take the print out of planned TNA
Take the final print out of TNA calendar.
Note: Get the work checked by your instructor.