                                 MODULE 16: Generation Transmission and
                                                       Distribution


           EXERCISE 106 :  Visit and Prepare layout plan/ single line

                                        diagram of the Thermal /Hydro /Nuclear

                                        power plant


             Objectives
           At the end of this exercise you shall be able to:
           •  visit and prepare layout plan of thermal power plant and identify the various stages in the plant
           •  visit and prepare layout plan of hydel power plant and identify the various stages in the plant
           •  visit and prepare layout plan of nuclear power plant and identify the various stages in the plant.

           Procedure

           1  Visit the stages of a thermal power plant i.e.
              a  Coal and ash handling arrangement
              b  Steam generating plant

              c  Steam turbine
              d  Alternator
              e  Feed water supply
              f  Cooling arrangement

           2  Identify the following constituents of a steam generating plant and write down their functions in Table 1.
                                                         Table 1
                                    Constituents               Type             Function

                              Boiler

                              Super heater

                              Economizer

                              Air pre-heater

                              Turbine

                              Condenser


                              Cooling tower

                              Water treatment chamber














                                                           285