Page 58 - CITS - Electrician - Trade Practical
P. 58

ELECTRICIAN - CITS




           TASK 3: Testing of Electrical wiring and connecting to main supply service line
           1  As per IE rules, a tests are to be conducted on completed Electrical wiring before connecting to the main
              supply service line.

           2   Conduct the continuity test of wiring with multi meter/test lamp by closing all switches and shorting all light
              points & socket points.
           3   Conduct short circuit test of wiring with multi meter/test lamp by keeping all switches OFF and all light points
              & socket points open.
           4   Conduct earth continuity and earth leakage test of wiring with megger.
           5   After satisfactory test results connect the electrical wiring supply mains through the protective fuse & MCB’s.
           6   Test all the electrical points, socket points for working condition.

           Safety precautions
           1   Use proper and insulated tools.
           2   Maintain proper dimensions between each electrical point.
           3   Fix the conduits, casing and electrical accessories tightly.
           4   Never make joints in electrical wiring.

           5   Never connect the wiring to the supply mains without conducting tests.

                                                                                 Short circuit test





















           Insulation resistance test between conductors






























                                                           41

                                    CITS : Power - Electrician & Wireman - Exercise 21
   53   54   55   56   57   58   59   60   61   62   63