           Step 2: Prepare a layout of wiring on the building plan. (Fig 3)


             Fig 3



























           Step 3: Calculate the total connected load and to decide whether it is 3phase or single phase.
           Step 4:  Prepare a circuit diagram showing the connections and number of lighting and power circuit(cubical
           wiring model). (Fig 4)


               Fig 4






























           Step 5: Prepare a list of electrical accessories to be procured.

           Step 6: Calculate the length of different sizes of cable required, based on the load, voltage drop and number of
           cables in each circuit run.
           Step 7: Calculate the length of different sizes of batten / PVC casing and capping / Metal conduit required based
           on the load, voltage drop and number of cables in each circuit run.
           Step 8: Prepare a list of hardware like a screw, nails etc. required to execute the job.