9 Position the earthing braid over the copper tape screen.
10 Connect the braid to the copper tape screen with the roll force spring.
11 Fill the cavities of the lug with red mastic tape
12 Wrap around the exposed conductor the red mastic tape stretching it, till reaching the lug barrel diameter
and wrap mastic tape around the lug barrel.
13 Apply a layer of red mastic tape starting from cut outer sheath till covering the previous applied layer of
mastic tape.
14 Apply the stress relief mastic pad, lightly stretched, starting from the cut outer sheath.
15 Slide the outer heat shrinkable red tube (stress control + insulation) till the TOP edge of red mastic tape
applied over the cable lug.