Page 184 - CITS - Fitter Trade Pactical - Volume - 2
P. 184

FITTER - CITS


           EXERCISE 52 : Depositing bead on aluminium sheet 2mm
                                      thick - position flat



            Objectives

           At the end of this exercise you shall be able to
           •  weld fusion runs with filler wire on aluminimum by TIG welding process in flat position.
























          Job Sequence

           1  Prepare the aluminimum sheet as per dimensions.
           2  Clean the surface with the stainless steel wire brush.
           3  Also do the chemical cleaning with acetone/alcohol to remove the grease and surface oxide.

           4  Draw parallel lines and punch the lines  as per  dimensions.
           5  Set the job in flat position.
           6  Select the power supply as follows:
              –  In case of helium as shielding gas use DCEN.

              –  In case of Argon as shielding gas and use AC power source. Majority of welding is done using argon gas.
           7  Set up the GTA welding plant as per the Fig.1.
           8  Select the type and size of tungsten electrode, current, gas flow rate and set them on the machine.
           9  Select aluminium filler wire. 1.6mmf with 5% silicon.
           10 Switch on the machine and strike the arc.

           11 Deposit fusion run with filler wire using leftward welding technique.
           12 Clean and inspect the weld job.


















                                                           169
   179   180   181   182   183   184   185   186   187   188   189