Page 265 - CITS - Welder - Trade Practical
P. 265
WELDER - CITS
EXERCISE 65: Make Square butt joint on MS sheet 2 mm
in Vertical position by GTAW.
Objectives
At the end of this exercise you shall be able to
• produce molten pool of required size by the manipulation of torch
• add filler metal at the required rate and place by manipulation the filler rod
• deposit fusion run with filler rod in flat position and maintain uniform arc travel speed
• clean and inspect the deposited beads for surface defects.
Job Sequence
• Cut the plate by using hacksaw cutting as per drawing
• Set the sheets and tack weld in the form of a “Square butt” joint on the welding in flat position
• Fill the crater
• Manipulate the torch and filler rod in the correct position with respect job
• Stop the weld at the left-hand edge of the joint after filling up in the crater at the end of the weld
• The angular distortion between the vertical and horizontal sheets of the Butt joint is automatically controlled
• The current set is 10 to 15 ampere
• At the end of the welding perform the carter filler treatment by repeating the torch switch ON-OFF
• Cut the arc and hold at the finishing point unit molten metal solidifies
• Visual inspection: slight convexity ,uniform width ,uniform ripples And free from under cut at the toes of the
weld indicate a smooth.
248