            Job Sequence

           •   Prepare and clean the plates.
           •   Set the Tee joint as per drawing and tack weld (Fig 1)
           •   Fix the joint in horizontal position.
           •   If DC machine is used, connect the electrode to the negative and use short arc to control arc blow.

           •   To avoid distortion due to contraction preset the plates such a way that the angle of the tack welded joint is
              increased to 92° to 93° on the welding side.
           •   Deposit the root run without weaving.

           •   Hold the electrode at the center of the joint and start from leftward and use proper technique to avoid excessive
              metal deposition at the bottom of the plate.
           •   Deslag and clean the root run.

           •   Deposit the second and third run using stringer bead technique covering the previously laid bead partially and
              the plate surface.